Federal Manager's Daily Report

The Department of Energy has run into substantial cost

and schedule overruns on many of its major projects —

$400 million and up — largely due to contract management

problems, the Government Accountability Office has

reported.

It said the department could use performance incentives

to control costs and schedules by developing guidance

and assigning responsibility for reviewing a contract’s

project management provisions prior to award.

Because DoE has awarded nearly half of the 33 major

projects GAO studied that use a schedule or other

performance incentive, but not “an associated cost

incentive or constraint,” it makes it possible for a

contractor to receive full fees while over-running costs

as long as it meets schedule baselines, according to

GAO-05-123.

Further, it said DoE “has relied on un-validated

contractor data to monitor contractors’ progress in

executing major projects and to award fees for performance.”

After a self-assessment of contract administration in

2002, Energy determined that field personnel relied too

much on contractor accounting systems, and data collected

by contractors to assess contractor performance, “without

significant validation of those data” and the problem

could be continuing, GAO said.

It recommended that DoE require contracting officers to

receive training to assess whether contractor project

management systems are adequate and produce good data

to measure progress.